Determine a need for the project
Define the study area
Gather data, identify constraints, and propose preliminary alternative route segments
Invite public involvement
Evaluate and refine preliminary alternative segments and combine them into primary alternative routes
Evaluate primary alternative routes using environmental/land use criteria, including consideration of factors in the following categories:
Complete an environmental assessment report and select the preferred route based on factors in categories such as:
Recommend the preferred route to the Citizens Advisory Committee for comment.
Recommend the preferred route to CPS Energy Board of Trustees for approval.