MORE SEARCH OPTIONS  
Add CPS Energy to your FacebookCPS Energy on Twitter
 
 
 

Frequently Asked Questions about the Marbach Road-Hunt Lane Substation Relocation Project


1. What is the need for the project?

Replacement of the existing Marbach Road substation with the new Hunt Lane substation is required to: (1) improve power reliability and reduce risk of outages due to flooding conditions; (2) support continued growth of customer load/energy demand; and (3) improve reliability through replacement of aging substation infrastructure.

Significant residential and commercial development in the area surrounding the Marbach Road substation has caused redistribution and concentration of floodwaters.  The Marbach Road substation has experienced significant and increased flooding over the past twenty years.  The following chronology depicts the flood events and responsive actions:

  • Late 1967 - Substation constructed.
  • May 1987 – Flood waters flowed into the substation, causing equipment damage and interruption of service to customers.  A hydrologic study was commissioned to determine the cause of the flooding and possible solutions.  The study concluded that flood waters would rise from backup on the downstream drainage and that flooding could not be prevented by improvements on CPS Energy property.  No corrective action was taken, as it was believed to be a rare occurrence.
  • October 1994 – Flood waters flowed into the substation, causing equipment damage and interruption of service to customers.  CPS Energy reviewed the 1987 hydrologic study and studied the possibility of replacing the driveway culvert with a free-standing bridge.  It was determined, due to infrequency of flooding, that the solution presented offered limited benefits in comparison to the cost of implementation.
  • Early 1998 – Changes were made to EPA’s Spill Prevention, Control and Countermeasure (SPCC) requirements, forcing installation of a 3-foot flood wall and imbiber oil-separating gravity drains.  Drains include check valves to stop back flow into the substation if flood water rise above substation grade.  Flood wall will act as containment until water recedes. 
  • October 1998 – Flood waters flowed over the newly installed flood wall, damaging substation equipment and interrupting service to customers.  This led to an engineering review and recommendation for an additional wall extension.
  • Early 1999 – A flood wall extension was added.  Review of hydrologic parameters in original study indicated run-off upstream of substation was increased due to land development.  A new hydrologic analysis indicated the extension should protect the substation against a 100-year flood.
  • Early 2000 - Limited drainage through imbibers led to high water inside the flood wall, due to unusually fast/dramatic rainfall on the substation site and runoff from subdivision.  Imbibers were replaced with simple oil-skimming plates.  Electric pumps were installed to remove water when the flow was impeded by high water outside flood wall.
  • July 2002 – Flood waters flowed over the flood wall extension, damaging substation equipment and interrupting service to approximately 6,400 customers.  It took approximately 2 hours to restore service to all of the customers.  No corrective action was taken for stream flooding, because any additional extension to the current flood wall would restrict access from the Hunt Lane entrance.  The rear entrance is intended as an emergency entrance and does not accommodate large construction and maintenance equipment.  A diesel powered pump was installed because flooding cut power to the electric pumps.
  • May 2007 – A plan was developed to replace Marbach Road substation with the new Hunt Lane substation.  With continued development in the area, it is anticipated that the risk and the severity of flooding events will only continue to increase.  The flooding events have caused interruption of service to customers, shortened equipment life spans, extended outages for cleanup and repair of damaged equipment, and a risk of damage to additional/near-by equipment that could have caused additional customer outages.

    Internal studies showed that as flooding severity increases, extended Marbach Road substation outages will result in additional and extended customer outages.  In particular, the area between Marbach, Bandera, Anderson and Cagnon substations is at risk of no service for an extended period of time.

    Over the next five years, continued development is expected in the area served by the Marbach Road substation.  This additional development will increase the area’s electrical demand by approximately 17 percent.  An additional substation distribution transformer is required to meet demand levels by the year 2009.  Also, beginning in 2009, aging substation equipment, such as the switchgear supplied by transformers #2 and #3, will require replacement to ensure reliable operation.
  • July 2007 - Flood waters flowed over the flood wall extension, damaging substation equipment and interrupting service to approximately 7,000 customers.  It took approximately 3 hours to restore service to all of the customers. 
  • August 2007 – Flood waters flowed over the flood wall extension, damaging substation equipment and interrupting service to approximately 7,000 customers.  It took approximately 3 hours to restore service to all of the customers.

Each of the above-listed flooding events required approximately 60 hours of round-the-clock work and two additional weeks of normal work to restore the substation equipment to normal operating conditions.  During this time period, the customers served by the substation were at an increased risk of extended outages.

As a municipal electric utility, CPS Energy must represent the interests of all customers by choosing the most cost effective solution to identified needs.  The Hunt Lane substation will facilitate transfer of load-serving functionality from the Marbach Road substation, effectively eliminating the risks associated with anticipated future flooding.  The Hunt Lane substation will be constructed to accommodate the additional substation distribution transformer required for the increasing electrical demand of the area.  The Hunt Lane substation will also be constructed with newer equipment to replace the aging and flood damaged Marbach Road substation equipment.  It is recommended to construct the new Hunt Lane substation by October 2009.

3. Were any other alternative sites considered?

  • Initial Considerations – The property between Hunt Lane & Ellison Drive, containing the four existing 138-kV transmission lines, was the obvious first consideration due to the current CPS Energy property ownership.  The substation can be constructed above the flood plain within the existing property and adjacent to current property owners.  Additionally, the site was chosen because it presents the least expensive alternative for connection to the existing distribution hub.  Identification of any other location was dismissed due to: the possibility of additional transmission being located adjacent to currently nonadjacent property owners, the substation site being located adjacent to either currently adjacent or nonadjacent property owners, and the additional cost to extend the distribution lines a farther distance from the existing distribution hub.
  • Move the substation closer to Ellison Drive – The properties on either side of Ellison Drive are sufficient for construction of a substation, because they are not located in a flood plain.  However, the substation property would have to be acquired from the current property owner and the location would be adjacent to either currently adjacent or nonadjacent property owners.  In addition, there is significant additional cost to extend the distribution lines an additional 3,000 feet from the existing distribution hub to an Ellison Drive site.  Any other possible location farther west along the existing transmission lines will present the same difficulties and greater expense for distribution line extensions.
  • Relocate the substation to the SAWS property, south of the existing substation – There is a site located on the southeast portion of the SAWS property that is sufficient for construction of a substation, because it is not located in a flood plain.  The site would have to be acquired from SAWS.  To facilitate this location, a new transmission line would have to be constructed from the existing transmission line, south of the existing Marbach Road substation, to the new location.  The transmission line would require a routing/siting analysis to determine a route, would be routed adjacent to currently nonadjacent property owners, would be located within the existing flood plain, and would significantly impact the cost of the project.  In addition, there is significant expense required to extend overhead and underground distribution lines from the existing distribution hub, through a flood plain, to the SAWS site.  Locating these distribution lines through a flood plain will increase the risk of power outages and create issues associated with emergency maintenance operations.

4. Can modifications be made to the drainage system at the existing Marbach Road substation?

A drainage improvement project could improve flooding conditions at the existing Marbach Road substation, however the substation’s proximity to the 100-year flood plain makes it impossible to flood-proof the substation. While the substation’s original placement had only moderate risk of flooding, development and changes to the nearby grading over time have significantly contributed to flooding problems. There is no expectation that this could be changed.  With a continued risk of flooding, the substation remains vulnerable to excessive power outages and flood damage.  In addition to the expense of improving the drainage system, there are multiple projects required within the existing Marbach Road substation to replace aging substation infrastructure and to support continued development in the area.

Previous attempts to keep flooding outside the substation footprint have failed.  The streambed on CPS Energy property was improved and a barrier wall was constructed around the substation, but recent flooding has increased in severity.  Flooding arises not only from the adjacent streambed, but also from runoff from the adjacent subdivision.

A drainage improvement project for the Marbach Road substation would have to be undertaken by the City of San Antonio (CoSA).  The project would undergo prioritization by CoSA and, if selected and funded, would follow the same process as other drainage projects.  This requires an extensive hydrologic study of the adjacent watershed, choice and engineering of drainage improvements, approval by affected land owners and the Army Corp of Engineers, acting on behalf of the Federal Emergency Management Agency.  The proposed project would require improvements on CPS Energy property and non-CPS Energy / non-CoSA properties.  Easements must be acquired on properties that require drainage improvements.  The drainage improvement project must provide proof that it would not adversely affect any other properties downstream.  If the drainage improvement project receives the required authorizations, it is expected that completion of the project may be accomplished within a five year timeframe.

The EPA has mandated that facilities with the possibility of releasing petroleum fluids into waterways must possess a preventative system.  Electric substations, such as the Marbach Road substation, contain insulating/cooling oil used in power transformers.  The system must be operational for a 100-year flood event.  The Marbach Road substation is within a 100-year flood plain.  Therefore, flood waters must be kept out of the substation for the spill containment system to be functional.  An additional concern is that the substation has experienced flooding conditions greater than a 100-year flood event.

A drainage improvement project would conceptually alleviate the risks associated with a selected flood event.  However, the drainage improvement project would not eliminate the substation’s vulnerability to larger flood events brought on by continued development, greater than 100-year rainfall amounts, or possible changes to the planned operation of the drainage system.  Since flooding remains a conceivable risk, based on best engineering practices, the substation should be relocated to a site well above the 100-year flood plain.

5. Can the existing Marbach Road substation be raised above the flood plain to prevent flood waters from entering the substation?

Raising the elevation of the existing Marbach Road substation can improve flooding conditions, but the substation’s proximity to the 100-year flood plain makes it impossible to flood-proof the substation.  With a continued risk of flooding, the substation remains vulnerable to power outages and flood damage.  Raising the substation’s elevation would displace floodwater, both on CPS Energy and adjacent property, thereby requiring drainage system improvements similar to the aforementioned process.  Raising the substation’s elevation would require a complete rebuild of the existing substation.  The substation would have to remain energized during the rebuilding operation; thereby costs would be significantly greater than relocating the substation.  In addition, adjacent transmission towers would require modifications or replacement, increasing the project costs further.

Raising the elevation of the existing Marbach Road substation would conceptually alleviate the risks associated with a selected flood event.  However, the elevation change would not eliminate the substation’s vulnerability to larger flood events brought on by continued development, greater than 100-year rainfall amounts, or possible changes to the planned operation of the drainage system.  Since flooding remains a conceivable risk and with the project cost anticipated to be significantly greater than relocation, it is practical to relocate the substation to a site well above the 100-year flood plain.

6. Can taller barriers be installed around the existing Marbach Road substation to prevent flood waters from entering the substation?

Installing taller barriers around the perimeter of the existing Marbach Road substation can improve flooding conditions, but the substation’s proximity to the 100-year flood plain makes it impossible to flood-proof the substation.  With a continued risk of flooding, the substation remains vulnerable to power outages and flood damage.  Installing taller barriers also would displace floodwater, thereby requiring drainage system improvements similar to the aforementioned process.  The existing flood wall has created accessibility issues and installation of a taller barrier would make access to the substation even more difficult, not only for the larger equipment, but also for the smaller vehicles used for more frequent construction, maintenance, and operations functions.  In addition to the expense of installing taller barriers and improving the drainage system, there are multiple projects required within the existing Marbach Road substation to replace aging substation infrastructure and to support continued development in the area.

Installing taller barriers around the perimeter of the existing Marbach Road substation would conceptually alleviate the risks associated with a selected flood event.  However, the increased flood wall height would not eliminate the substation’s vulnerability to larger flood events brought on by continued development, greater than 100-year rainfall amounts, or possible changes to the planned operation of the drainage system.  Since flooding remains a conceivable risk using best engineering practices, the substation should be relocated to a site well above the 100-year flood plain.

9. What are the health issues and concerns with the electric and magnetic fields (EMF) produced by the new substation located on the existing transmission easement?

Currently, there are four existing 138 kV transmission lines in a 200-foot transmission easement. These transmission lines currently produce EMFs whose strength diminishes as a function of distance. However, transmission lines and substations are not the only source producing EMFs. Neighborhood distribution lines on wood poles, which usually carry less voltage than transmission lines, also generate EMFs. For that matter, any household appliance will generate a certain amount of EMFs.

EMFs are generated by electrical currents used in everyday life and pinpointing a single source is difficult because humans may be exposed to a multitude of possible sources each day.  All household appliances generate an electric field when plugged into an electrical outlet, but the magnetic field is not generated until the appliance is operating.  Exposure among different homes is different because it can be affected by the wiring system and appliance usage.  Appliances from different brands of appliances may also generate different EMF intensities.  EMFs can be generated by common items such as televisions, can openers, electric clocks, computer monitors, etc.  However, some studies have indicated that cell phones, electric blankets and hair blow driers can have more of an effect since they are held closer to the human head.

Electricity is carried around the city on various types of power lines, and substations are used to step up or step down the voltage of the power.  The electric and magnetic fields generated by power lines are highest directly under the power line where the conductors are located and drop the further you move away.  Therefore, there is not much human exposure since much of the EMF is directly under the power line. Most substations do not produce very large EMFs; the fields are primarily generated by power lines entering them.  The fields that are produced by substations fall rapidly within the perimeter fence.  It would be difficult to distinguish fields present in homes from the fields coming from the substation.

 

Learn more about electromagnetic fields