Scheduled maintenance planned starting 7:00pm Friday, December 14 through 7:00am Sunday, December 16.  During this time, our automated phone system, Manage My Account, online forms, and all CPS Energy web portals will not be available. We will not be able to take payments in any form during this time. Thank you for your patience.

Inwood/Deerfield Neighborhoods

 
 

COMMITMENT TO RELIABLE SERVICE

In an effort to continuously improve the delivery and reliability of electric service to our community, we are performing a multi-phase project to help mitigate the risk of power outages in northwest San Antonio.

 

SCOPE OF PROJECT 

The work consists of extensive tree trimming in contact with overhead lines and installing animal guards at our nearby substation. As phases of our work are completed, area residents can expect to see an improvement to the reliability of their electric service.

 

ESTIMATED TIMELINE

This project is expected to begin January 2018 and be completed by March 2018.

 

PROJECT UPDATES

01/02/2018: Reliability concerns investigated

01/04/2018: HOA meeting

01/26/2018: Project completion dates established

03/05/2018: Project completed

 

PROJECT CONTACT

For more information, please contact us at 210.353.2222