In an effort to continuously improve the delivery and reliability of electric service to our community, we are performing a multi-phase project to help mitigate the risk of power outages in northwest San Antonio. The work consists of extensive tree trimming in contact with overhead lines and installing animal guards at our nearby substation.

As phases of our work are completed, area residents can expect to see an improvement to the reliability of their electric service.

For questions or concerns regarding this project you can contact John Moreno via email or by calling 210.555.5555.

Timeline of project:

  • 01/02/18 - Reliability issues being investigated
  • 01/04/18 - HOA meeting
  • 01/26/18 - Project completiong dates established
  • 02/28/18 - Estimated project completion date