Large load customer growth

We are taking swift action to streamline and accelerate the rapid increase in demand from our large load customers, specifically data centers, focusing on improving the customer experience starting with these 4 key areas.
Large load customers are those requiring more than 40 MW of power.

Giving you a better customer experience

 

Follow our six-step process for interconnection

Each Large Load customer project is unique, and the overall timeline will be communicated on a case-by-case basis. The overall project and individual process step durations are driven by factors such as system capacity, geography, and technical scope. 

Large load customer growth FAQ

One or more Facilities at a common development with an aggregate demand load greater than or equal to 40 MW behind one or more common Points of Delivery.

For facilities requiring less than 40MW, the step-by-step design process can be accessed by clicking here: New Commercial Construction.

Yes, CPS Energy is assessing fees for customers requesting an engineering and planning study for interconnection requests equal to or exceeding 40 megawatts (MW). Our Study Fee Schedule is shown below. Please note that these fees are in addition to any ERCOT levied fees, and CPS Energy will update the fee structure annually to ensure cost recovery for interconnection study activities.

For projects with loads greater than 75 MW, the Pre-LLIS Screening Study is offered to identify the most efficient Point of Interconnection (POI) in scenarios where multiple transmission lines are in the vicinity of the property. All projects larger than 75 MW will require the ERCOT Large Load Interconnection Study. Please note that these fees are in addition to any other ERCOT-levied fees, and CPS Energy will review and update the fee structure annually to ensure full cost recovery for interconnection study activities. CPS Energy also reserves the right to determine any additional study requirements and apply corresponding fees on a case-by-case basis.

Study Fee Schedule
Study Name Applicable Size Cost
End-User Interconnection Study* ≥ 40 MW and < 75 MW $75,000
Pre-LLIS Screening Study ≥ 75 MW $75,000

ERCOT Large Load Interconnection Study

(LLIS)*

≥ 75 MW $150,000**

* Required Study based on applicable load

** Per Point of Interconnection (POI)

You can contact the Business & Economic Development team at B&[email protected].

The Electrical technical specification form will collect technical information needed to begin the process.

Each Large Load customer project is unique, and the overall timeline will be communicated on a case-by-case basis. The overall project and individual process step durations are driven by factors such as system capacity, geography, and technical scope.

We'll need to study your specific load request to help you understand what capacity will be available and when it might be available. To get the process started, you can send it to B&[email protected] or fill out our Electrical technical specification form.

CPS Energy is currently exploring new technologies and process improvements to adapt to changing grid requirements. For more information, please see the Data center & large load presentation has more information.

Large load customer resources