Legend Falls Substation & Transmission Line Project

 
 

CPS Energy is proposing to construct a new 138 kV substation and approximately two miles of new 138 kV transmission corridor in Medina County. The proposed transmission lines will require new Right of Way (ROW).  One double-circuit transmission line will connect the new substation to the CPS Energy transmission system and the other single-circuit transmission line will connect the CPS Energy substation to the STEC San Geronimo substation.

The Electric Reliability Council of Texas (ERCOT) endorsed this project as a needed transmission system improvement on the CPS Energy system on February 16, 2024.

Update 04/06/26- CPS Energy has filed for a docket number with the Public Utility Commission of Texas (PUC). The docket number is 59549 and can be found on the PUC Interchange website here.

Digital copies of the complete application and attachments are available on this website, and the PUC Interchange. A physical copy of the documents is available for public viewing at:

CPS Energy, 500 McCullough, San Antonio, TX 78215
and
Potranco Branch Library, 8765 TX-151, San Antonio, Texas 78245 

Notice packages (Attachment 5) for this project have been mailed out via first class mail to all directly affected Landowners. If you wish to participate in this proceeding by becoming an intervenor, the deadline for intervention in the proceeding is May 6, 2026, and the PUC should receive an electronic filing or letter from you requesting intervention by that date. More information about the PUC’s filing process can be obtained at the PUC’s website here. Instructions for using the PUC Filer are available here. For assistance with an electronic filing, please contact the PUC’s Help Desk at (512) 936-7100 or [email protected].

You may call, write, or email: 

CPS Energy 
Cody Lansford
Project Manager
 
Legend Falls Substation & Transmission Line Project 
Mail Code RT0801
500 McCullough Ave.
San Antonio, Texas 78215
(210) 353-2363
[email protected]